Highway 84 Corridor Wastewater System Improvements – Phase 3A

This portion of the Hwy 84 Corridor Wastewater System Improvements project includes constructing 8, 200 linear feet of new 24-inch wastewater line on Val Verde Rd., Hwy 84, and Harris Creek Rd. This new 24-inch wastewater line replaces older wastewater lines and increases the system capacity for the area.

Projected Start/End Dates

This project began construction in March 2020 and is expected to be complete during Summer 2021.

Projected Cost

$4.8 million

Anticipated Impact to Residents

Beginning at the end of August 2020, varying portions of Harris Creek Rd. will be closed to through-traffic, with detour routes set-up. The work (and so also, the area of closure) will start at the southernmost section, prior to Hidden Creek Rd., of Harris Creek Rd. and move north, towards Hwy 84.

Primary Core Issue Addressed

Water Master Plan: Asset Renewal