Chimney Hill

Storm drain improvements will be made, increasing drainage flow capacity to prevent the flooding of local homes.  Due to their proximity, water and wastewater lines will also be replaced at the same time.

Projected Start/End Dates

This project is currently in design.

Projected Cost

Water and wastewater lines –  $2 million
Storm drain improvements – $1.39 million
Total – $3.39 million

Anticipated Impact to Residents

Some street closures are expected.

Primary Core Issue Addressed

Wastewater Master Plan: Critical Capacity Upgrades

Download the Project Information Sheet