Brentwood and Cougar Ridge Wastewater Improvements

The Brentwood and Cougar Ridge Sanitary Sewer Improvements project will result in improved flow and increased capacity for an existing residential neighborhood and an expanding residential area. The project includes the replacement of approximately 2,128 feet of 12” wastewater line with 16” line and the replacement of approximately 395 feet of 8” wastewater line.

Projected Start/End Dates

Work on this project began in December 2019 and is expected to be completed by June 2020.

Projected Cost

Approximately $1.7 million

Anticipated Impact to Residents

There will likely be some temporary detours as work requires them.

Primary Core Issue Addressed

Wastewater Master Plan: Asset renewal